Arrival of two 60 MVA transformers completes the high-voltage long-lead package to expand the site to up to 110 MW of total capacity, including 40 MW already energized Vancouver, British Columbia--(Newsfile Corp. - November 10, 2026) - Bitzero Holdings Inc. (NASDAQ: AIBZ) (CSE: AIBZ.U) (FSE: 000) ("Bitzero" or the "Company") today issued the following shareholder letter from Founder, Chair and Chief Executive Officer Mohammed Bakhashwain. Dear Shareholders, The two 60 MVA transformers ordered for our flagship data center site in Namsskogan, Norway (the "Namsskogan Site") have arrived in Norway.